Polk County, Florida has 300 MW of data centers on record, planned to operating, across 3 records, against 6.7 GW of generation operating inside the county. The queue adds 114.7 MW of planned generation across 3 projects. That is 6.8% of Florida's data center MW.
Polk County and its neighbors
Counties shaded by data center MW on record, planned to operating. 6 of its 7 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 300 MW of data centers against 6.7 GW of plants, with 114.7 MW more planned.
Data centers by status
3 records, 300 MW
The data center pipeline
1 record list a year online or expected, from 2014 to 2014. No record lists a year at or after the snapshot. 2 records list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2014 | 1 | 0 |
Who is building in Polk
Data center developers by MW on record. Top 3 of 3.
View as table
| Developer | Sites | MW |
|---|---|---|
| Cielo Digital Infrastructure | 1 | 300 |
| Bohler Places LLC | 1 | 0 |
| Cologix | 1 | 0 |
Power generation in the county
91 plants operate inside Polk County, 6.7 GW. The queue adds 114.7 MW across 3 projects.
Operating and planned generation by technology
MW in Polk County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Natural Gas | Operating | 46 | 5,745.7 |
| Solar | Operating | 15 | 579.7 |
| Solar | Planned | 2 | 94.7 |
| Waste Heat | Operating | 7 | 255.4 |
| Battery Storage | Operating | 1 | 40 |
| Battery Storage | Planned | 1 | 20 |
| Oil | Operating | 22 | 55 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2026 | 2 | 94.7 |
| 2027 | 1 | 20 |
Polk County against its neighbors
Hillsborough has the most data center MW among the neighbors, 12 MW, 4% of Polk County's. 6 of the 6 have more generation operating than data center MW on record.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Polk County this page | 3 | 115 | 0.04x | ||
| Hillsborough | 2 | 95 | 0x | ||
| Osceola County | 0 | 150 | 0x | ||
| Hardee County | 0 | 0 | 0x | ||
| Pasco County | 0 | 629 | 0x | ||
| Highlands County | 0 | 150 | 0x | ||
| Lake County | 0 | 0 | 0x |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
7 counties shownWhat changed since June 4, 2026
2 projects in Polk County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Polk County
Project, what changed, technology, MW and the dates that moved, for all 2 changes.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Polk County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 97 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Polk County
We email you when a data center or power project in Polk County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Polk County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.