Pulaski County, Arkansas
Pulaski County, Arkansas has 155 MW of data centers on record, planned to operating, across 4 records, against 663.6 MW of generation operating inside the county. The queue adds 120.4 MW of planned generation across 2 projects, 1 of them past its listed in-service date.
Pulaski County and its neighbors
Counties shaded by data center MW on record, planned to operating. 3 of its 6 neighboring counties have pages of their own. The rest are in the member database.
Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers
of the generation operating in the county is matched by data center MW on record: 155 MW of data centers against 663.6 MW of plants, with 120.4 MW more planned.
Data centers by status
4 records, 155 MW
The data center pipeline
1 record list a year online or expected, from 2027 to 2027. The largest expected additions are 150 MW listed for 2027. 3 records list no year.
Data center MW by year online or expected
Records not cancelled, by listed year. 2026 onward is planned or under construction.
View as table
| Year | Records | MW |
|---|---|---|
| 2027 | 1 | 150 |
Who is building in Pulaski
Data center developers by MW on record. Top 4 of 4.
View as table
| Developer | Sites | MW |
|---|---|---|
| Avaio Digital Partners | 1 | 150 |
| Tierpoint | 1 | 5 |
| 1 | 0 | |
| Willowbend Capital | 1 | 0 |
Power generation in the county
22 plants operate inside Pulaski County, 663.6 MW. The queue adds 120.4 MW across 2 projects, and one of them is past its listed in-service date.
Operating and planned generation by technology
MW in Pulaski County
View as table
| Technology | Status | Projects | MW |
|---|---|---|---|
| Natural Gas | Operating | 10 | 600.8 |
| Solar | Operating | 4 | 12.6 |
| Solar | Planned | 2 | 120.4 |
| Hydro | Operating | 2 | 45.4 |
| Landfill Gas | Operating | 6 | 4.8 |
Planned generation by listed in-service year
MW. Years before 2026 are past due.
View as table
| Year | Planned projects | MW |
|---|---|---|
| 2025 | 1 | 115.5 |
| 2026 | 1 | 4.9 |
Pulaski County against its neighbors
None of the 3 neighboring counties with a page lists a data center record. Jefferson County has the most operating generation among them, 2.1 GW.
| County | Data center records | Data center MW | Operating generation MW | Planned generation MW | Data center MW per MW operating |
|---|---|---|---|---|---|
| Pulaski County this page | 4 | 120 | 0.23x | ||
| Jefferson County | 0 | 2,835 | 0x | ||
| Grant County | 0 | 640 | 0x | ||
| Lonoke County | 0 | 968 | no operating MW |
Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.
4 counties shownWhat changed since June 4, 2026
1 project in Pulaski County moved between the two snapshots. Counts and MW are below; the projects themselves are for members.
Every change in Pulaski County
Project, what changed, technology, MW and the dates that moved, for all 1 change.
| Project | Change | Technology | MW | Previous date | New date |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see the project behind each change, its developer and the dates that moved.
Every record in Pulaski County
Campus or project name, developer, status, MW, year and the developer’s contacts, for all 28 records. Filter, sort and export to Excel.
| Project or campus | Developer | Status | MW | Year | Contacts |
|---|---|---|---|---|---|
Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.
Get alerts for Pulaski County
We email you when a data center or power project in Pulaski County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.
Open every campus, project and contact in Pulaski County.
Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.