Ouachita County, Arkansas

Ouachita County, Arkansas has 9 power projects in the FieldProspects database: 5 operating plants totaling 144 MW and 4 planned projects totaling 900.8 MW. No data center record lists the county. Solar leads with 773.8 MW across 5 projects. 2 planned projects are past their listed in-service date.

Data as of Grid region: Midcontinent ISO (MISO)Refreshed monthly
9
power projects, planned and operating
900.8MW
planned generation, 4 projects
144MW
operating generation, 5 projects
2
planned projects past their listed in-service date
Map

Ouachita County and its neighbors

Counties shaded by data center MW on record, planned to operating. 4 of its 6 neighboring counties have pages of their own. The rest are in the member database.

Nevada Calhoun no data centers Columbia no data centers Ouachita no data centers Dallas Clark no data centers Union no data centers
no data center MWunder 100 MW100 to 1,000 MW1,000 to 5,000 MW5,000 to 15,000 MW15,000 MW or more no page yet

Data center records planned, under construction and operating, data as of October 8, 2026.Hover a county for its numbers

Headline finding
6.3times

more planned than operating generation in Ouachita County. 4 projects in the queue would add 900.8 MW to the 144 MW operating today, and 2 of them are past their listed in-service date.

Operating generation144 MW
Planned generation900.8 MW

Technology mix

9 projects, 1 GW planned and operating

Solar773.8 MW5 projects, 74%
Natural Gas136 MW1 project, 13%
Solar + Storage (Hybrid)130 MW1 project, 12%
One other technology5 MW2 projects, 0%
Which companies own these 9 projects?Project names, developers and contacts are for members.See what members get

Power generation in the county

5 plants operate inside Ouachita County, 144 MW. The queue adds 900.8 MW across 4 projects, and 2 of them are past their listed in-service date.

Figure 1

Operating and planned generation by technology

MW in Ouachita County

OperatingPlanned
SolarOperating 3 MW 2 projects
SolarPlanned 770.8 MW 3 projects
Natural GasOperating 136 MW 1 project
Solar + Storage (Hybrid)Planned 130 MW 1 project
Battery StorageOperating 5 MW 2 projects
View as table
TechnologyStatusProjectsMW
SolarOperating23
SolarPlanned3770.8
Natural GasOperating1136
Solar + Storage (Hybrid)Planned1130
Battery StorageOperating25
Operating: 144 MW. Planned: 900.8 MW. If every planned project is built, county generation would reach 1 GW.
Source. FieldProspects database: ISO/RTO interconnection queues, EIA-860M and public data center filings, data as of October 8, 2026.
Figure 2

Planned generation by listed in-service year

MW. Years before 2026 are past due.

Past dueDue 2026 or later
0200400600800 Snapshot year 236 2025 2026 665 2027
View as table
YearPlanned projectsMW
20252235.8
202600
20272665
2 projects, 235.8 MW, were due before 2026

Ouachita County against its neighbors

None of the 4 neighboring counties with a page lists a data center record. Union County has the most operating generation among them, 2.4 GW.

CountyData center recordsData center MWOperating generation MWPlanned generation MWData center MW per MW operating
Union County 0
0
2,430
1,470 0x
Ouachita County this page 0
0
144
901 0x
Clark County 0
0
76
0 0x
Calhoun County 0
0
12
1,060 0x
Columbia County 0
0
0
762 no operating MW

Data center MW counts records planned, under construction and operating. Generation is inside the county only. Neighbors without a page have fewer than three projects on record.

5 counties shown

Every record in Ouachita County

Project name, developer, status, MW, in-service year and the developer’s contacts, for all 9 records. Filter, sort and export to Excel.

Members only
County: Ouachita County, ARStatus: all except cancelledSort: MW, largest first 9 records
Project or campusDeveloperStatusMWYearContacts
9 records and 1 GW behind this preview

Rows are hidden on public pages. Members see every field and can export up to 1,000 rows a month on Solo, unlimited on Unlimited.

Request access

Get alerts for Ouachita County

We email you when a data center or power project in Ouachita County is added, changes status, signs an interconnection agreement or slips its date. One email per snapshot, only when something changed.

One email per snapshot, only when something changed. Unsubscribe any time.

Open every campus, project and contact in Ouachita County.

Solo is $250 a month for one user. Unlimited is $500 for your whole team. Cancel any time.