<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"><channel><title>FieldProspects: what changed in US power queues</title><description>Each time the FieldProspects database is refreshed, the new snapshot is compared with the one before it: projects added, came online, cancelled, agreements signed, construction starts and date slips.</description><link>https://fieldprospects.com/</link><item><title>What changed in US power queues, June 4 to October 8, 2026</title><link>https://fieldprospects.com/changes/2026-09-24/</link><guid isPermaLink="true">https://fieldprospects.com/changes/2026-09-24/</guid><description>Between June 4, 2026 and October 8, 2026: 587 projects added (89.4 GW), 311 came online (32.3 GW), 882 cancelled (180.2 GW), 179 signed interconnection agreements, 102 started construction, 1,020 slipped their in-service dates by a median of 182 days and 56 pulled forward. Data center records went from 1,705 to 3,671.</description><pubDate>Thu, 24 Sep 2026 12:00:00 GMT</pubDate></item></channel></rss>